Say this
Read it out, or put it in your own words. Stop and point at the real thing on this site wherever you can.
1. No second chances
You cannot see, hear or smell electricity. A shock can stop your heart, burn you deeply or throw you off a ladder or scaffold. Most site shocks come from ordinary things: a damaged lead, a wet plug, a tool with a cracked casing, or someone fiddling with the DB board. So we treat every cable as live until a competent person proves otherwise.
2. The DB board belongs to one person
Our temporary supply is controlled by a competent person appointed in writing, and it is inspected every week and written up. Nobody else connects, opens up or changes the DB board. Keep its door closed and keep it out of the rain. Never bypass an earth leakage unit because it keeps tripping. If it trips, it is telling us something is wrong, so stop and report it.
3. Check your lead and tool before you plug in
Every morning, look at your tool, its cord and plug, and your extension lead. Reject anything with cuts, bare wire, burnt marks, broken plugs or tape repairs. Never push bare wires into a socket. Tools must be plugged into a supply with earth leakage protection, or be marked as double insulated. If something is damaged or got wet, label it 'do not use' and hand it in.
4. Look after the leads
Run leads where they will not be driven over, walked through or cut by sharp edges. Keep them out of water and off wet slabs, and hang them up where you can. Do not overload multi-plugs or join lead after lead. Unplug by the plug, not by pulling the cord.
5. Look up and look down
Before work starts we must find out about any cables over, under or on the site. Nobody may come too close to an overhead power line, in person or with a ladder, scaffold tube, tipper body, crane boom or stack of material, without the line owner's permission. Do not dig until buried cables have been located. If you are unsure, stop and ask.
6. If someone gets a shock
Do not touch them while they may still be in contact with the power. Switch off at the DB board or pull the plug first. Then call the first aider and get medical help. Report it, so it can be written up and looked into.
Check on site today
- Look at the DB board: door closed, protected from rain, no loose wires, and the weekly inspection register up to date.
- Ask the appointed person to test the earth leakage unit with its test button.
- Check every extension lead and tool cord in use today for cuts, bare wire and tape repairs.
- Walk the lead routes: leads lifted off the ground, out of water and away from vehicle routes.
- Point out any overhead lines near the site and where ladders, scaffolds and trucks must not go.
- Ask whether any digging is planned and whether buried cables have been located.
Ask the crew
Open questions get people talking. Listen to the answers: they tell you what's really happening on site.
- What would you do if the earth leakage on the DB board kept tripping when you plug in?
- Where are the overhead lines on or near this site, and what work today could get close to them?
- Which of our leads or tools would you not trust right now, and why?
- If you found someone lying against a live cable, what is the first thing you would do?
Protective equipment for this job
- Normal site PPE: hard hat, safety boots and high-visibility vest
- Electricians use insulated tools and the protective equipment their own risk assessment calls for
What the law says
In our own words. Follow the links for the full wording.
- Construction Regulations, 2014, regulation 24: Electrical installations and machinery on construction sitesThe contractor must find and guard against any electrical cable or apparatus under, over or on the site, use equipment strong enough for site conditions, give control of temporary installations to a competent person appointed in writing, have temporary installations inspected at least weekly with findings recorded, and have operators check electrical machinery daily against a checklist before use.Read on 21 November 2026
- Electrical Machinery Regulations, 2011, regulation 10: Portable electric toolsA portable electric tool over 50 V to earth may only be used if it is on earth leakage protection, on its own isolating transformer, on an approved dedicated supply, or is marked as double or reinforced insulated. It must have a switch for safe starting and stopping, and the tool, cord and plug must be kept in good working order.Read on 21 November 2026
- Electrical Machinery Regulations, 2011, regulation 19: Overhead power linesNo one may build, place material or soil, or come in person or with objects within the minimum safety clearances of a power line, or make anyone else do so, without permission from the supplier or user operating the line.Read on 21 November 2026
Sign the register
Everyone who listened signs page 2 of the PDF: name, company or trade, signature. Keep it in the site's health and safety file. How to fill in the register.
Free from sitediary.co.za/toolbox-talks/electrical-safety/. The attendance register is page 2 of the PDF, or sitediary.co.za/toolbox-talks/attendance-register/. General safety information, not legal advice: follow your site's risk assessment and health and safety plan.
This talk is general safety information for South African sites, not legal advice. Your site's risk assessment, safe work procedures and health and safety plan come first. Written 21 November 2026 by Kindly Made from the sources linked above.